Association Coal-Fired Power Plant:
The Homer Electric Association
and the Alaska Industrial Development and Export
Authority (AIDEA) signed a Project Development Agreement in
November 2006 that will lead to the restart of the defunct
AIDEA-owned Healy Coal Plant, a 50-megawatt coal-fired power
plant located in Healy, Alaska, near the Usibelli coal mine,
just outside Denali National Park.
The Healy plant has sat idle since its construction in the
1990’s, largely because the “clean” components of its “clean
coal” technology failed to work. With its energy supply
contract with Chugach Electric Association expiring in 2014,
HEA is moving ahead with re-starting the Healy plant by
2009/10.
Status:
Litigation between the local electrical cooperative and
AIDEA has stalled HEA’s acquisition plans, but HEA
management continues to believe the legal issues will
clear-up in time for a 2009/10 start-up. See
http://www.homerelectric.com/Current%20News/HCCP.htm
Applicant:
Homer Electric Association, Alaska Industrial
Development & Export Authority (see
www.aidea.org/HealyCleanCoalProjectPage.html).